Lynemouth Power Station Biomass Conversion Project SP3, Port of Tyne

PROJECT PROFILE

PROJECT
Lynemouth Power Station Biomass Conversion Project SP3, Port of Tyne
CLIENT
Spencer Group
LOCATION
CDS Fabrication Shop and Port of Tyne
TONNAGE
997 tonnes
DATE
2016 – Ongoing

WORKSCOPE

CDS’ scope of works includes the design, detailing and full fabrication of steelwork gantries and trestles for a fully integrated and automated biomass rail-loading facility installed by Spencer at the Port of Tyne.

The system will allow wood pellets to be conveyed mechanically to one of three newly-built silos, each capable of storing 25,000 tonnes of material. The pellets will then be discharged from the silos via two conveying streams to a rail-loading facility, in order to take the material to Lynemouth Power Station.

Lynemouth Power Station Biomass Conversion Project SP3, Port of Tyne
Download Case Study
CDS is a member of the following: