York Field Development (Offshore and Onshore Easington East Yorkshire)

PROJECT PROFILE

PROJECT
York Field Development (Offshore and Onshore Easington East Yorkshire)
CLIENT
Centrica Energy
LOCATION
CDS Fabrication Shop and Site Construction at Onshore Terminal and Offshore Platform
VALUE
£15M

WORKSCOPE

CDS scope included the full fabrication and construction to mechanical completion of the Easington Terminal works and offshore hook-up of the York unmanned platform including by system:

Terminal works

  • Inlet area
    • New sphere receiver
    • Assessment and re-use of decommissioned slug catcher
  • Gas processing plant
    • Dehydration – new silica gel adsorption beds + regeneration facilities
    • Plot space – utilise space currently occupied by redundant equipment
  • Sales gas filters and metering
    • Sales gas filters
    • Sales gas metering runs and connection into NTS
  • Liquids handling
    • New condensate stabilisation, off-gas compression systems, existing condensate tankage
  • Tie-in and integration to existing methanol tankage, recovery and delivery systems for conveyance to platform
    • Tie-in and integration to existing corrosion inhibitor tankage and delivery systems
    • Tie-in and integration to existing waste water treatment and waste water outfall
  • Utility/safety systems
    • Tie-in and integration into the following existing system infrastructure:
      • Vent and blow-down systems
      • Firewater
      • Instrument air
      • Fuel gas, nitrogen
      • Drainage system
  • Offshore platform hook-up works (43m water depth, jacket 800t, deck 1200t)
    • 6 well slots
    • Crane, Pig launcher, Helideck, TEMPSC
    • Space for future tie-backs